Import a named .est file from WinEst

  1. Go to Projects.

  2. On the Projects page, open the project by selecting Enter on the project tile or the enter icon (Enter project icon.) next to the project row.

  3. Select Import Estimate from the toolbar.

  4. In the dialog, do the following:

    1. Select Trimble WinEst, and then select Next.

    2. Select the estimate that you want to import, and then select Next.

      Sage Estimating (cloud) displays a list of all WBS descriptions found in the estimate.

      You can also import a WinEst estimate from an exported file instead using the Upload File option.
    3. From the Bid Package dropdown, select the WBS description that corresponds to bid packages in the WinEst estimate.

    4. From the Phase dropdown, select the WBS description that corresponds to phases in the WinEst estimate.

    5. Select Next.

    6. If this is the first time you import an estimate or new cost category names appear in the imported file, do the following:

      1. For each category in the file, select the relevant Sage Estimating (cloud) cost category from the dropdown.

      2. If no relevant cost category exists in Sage Estimating (cloud), Admins and Librarians can create a new one by selecting Add New Category from the dropdown.

        This allows them to define a cost category and link it to the corresponding name in the imported file. Each cost category can only be mapped to one name in the file.

      3. Select Finish.

Next steps: When the import is complete, the Summary Sheet is populated with the bid packages, phases, and estimate items from the WinEst estimate. Expand a bid package to view its phases and associated budgets. By default, each phase budget is calculated from the total value of the items assigned to that phase in WinEst.

Estimate items, including quantities, category costs, WBS assignments, and scope information, are imported and associated with the appropriate bid package phases. Expand a phase in the Summary Sheet to view its imported scope information. You can use this information to verify that subcontractor bids cover the full scope of the phase.